Through the Konya Ereğli-Ivriz Left Bank Irrigation Renovation Project, which was awarded by DSI and financed by a World Bank loan, a pressurized irrigation system will be constructed by renovating the existing 15,280-hectare irrigation system that is currently irrigated by open ducts and canals. The project comprises a total of 505 kilometers of pipe installation, including approximately 64 kilometers of CTP pipes, 14 kilometers of steel pipes and 427 kilometers of PE-100 pipes, and the construction of one pumping station and one regulation reservoir. The project is planned to be completed and commissioned within five years.

Employer: DSI General Directorate
Location: Ereğli/Konya/Turkey